Important Information For Ekta Vihar Housing Scheme| Registration Information For Ekta Vihar Housing Scheme| Important Notice For Auction| New Township Policy, 2022 (8.9.2022) (F)| Details of unallocated commercial properties of the Authority| Map Approval on UPOBPS Portal| Important Points related to U.P. RERA

Costing

Land Rate

For the costing of Land, the land rate shall be taken as applicable on the date of Allotment.

Location Charges

If the plot is situated on a road having 18 meter or more width, 10% of the cost shall be paybale as location charges.

Corner Charges.

If the plot is a corner plot (i.e. the plot is situated on road from two sides), 10% shall be payable as corner charges

Park Facing.

If the Plot is facing any park, 5% shall be additionally payable as park facing charges

Combination

In case for any plot, all the above charges are applicable, the maximum charges applicable shall be 20%

Transfer of Property Charges.

In case, on demand of applicant, the property is changed, 15% of total value of transferred property shall be charged as transfer fee.

Cost of Additional Land In case

Theare of the plot is more than the standard/ allotted area, the cost of extra land shall be calculated with the land rate at the time of allotment for the area upto 10% increase, and for balance increased area, land rate shall be the current prevailing rates.

Costing For Houses

Generally the cost mentioned on the allotment letter is the estimated price of the House. The actual cost of the House is calculated when the actual expenditure of construction, duration of work and interest rate are received from the engineering section. The cost is calculated on the basis of actual cost of construction, interest for half of the duration, Consultancy, overhead charges and the cost of land.

Mutation

The mutation charges shall be calculated @ 1% of the current market price of the property.

Costing for Multistory Property

The costing of the multistory buildings are done similar to the houses as far as the construction is concerned. For calculation of the land cost following methodology is adopted